Perris High School Interim Housing

by | Oct 9, 2014 | 0 comments

Description

From the issuance of the Notice to Proceed on June 11th, 2014 through substantial completion on September 7th, 2014 Pro-Craft Construction successfully installed 1820′ of storm drain, 1060′ of sewer, 2200′ of fire water, 2,480 of domestic water, 700′ of natural gas, an offsite sewer connection and a 99 chamber storm water MC-3500 chamber system.

Scope

Fast Track Utility Project.

  • CategoryEducation K-12
  • LocationPerris, CA.
  • ContractorNeff Construction
  • OwnerPerris Union High School District
  • Completed2014